Dak Lak

Dak Lak

INTRODUCTION

Ayo Biomass’s second biomass plant is located in M’Drắk Commune, Dak Lak Province and was successfully commissioned in September 2025. With a capacity of 150,000 metric tons per year, the facility strengthens the company’s production footprint in Vietnam’s Central Highlands.

Developed under the guidance of Future Metrics, the plant follows international best practices in sustainability and operational efficiency.

John Swaan of Future Metrics on site, supporting commissioning activities in August 2025
John Swaan of Future Metrics on site, supporting commissioning activities in August 2025
Overview of Ayo Biomass’s second biomass plant in M’Drắk, Dak Lak
Overview of Ayo Biomass’s second biomass plant in M’Drắk, Dak Lak

PLANT HIGHLIGHTS

  • 📍 Location: M’Drắk Commune, Dak Lak Province
  • ⚙️ Capacity: 150,000 metric tons per year
  • 📅 Commissioning: September 2025

OPERATIONS & INFRASTRUCTURE

Raw material handling and operational activities at Ayo Biomass’s M’Drắk facility
Raw material handling and operational activities at Ayo Biomass’s M’Drắk facility
Hammer Mills at Ayo Biomass M’Drắk facility
Hammer Mills at Ayo Biomass M’Drắk facility
Dryers at Ayo Biomass M’Drắk facility
Dryers at Ayo Biomass M’Drắk facility
Pelletizing systems at Ayo Biomass M’Drắk facility
Pelletizing systems at Ayo Biomass M’Drắk facility

The M’Drắk plant is equipped with modern biomass processing and handling systems, designed to ensure consistent quality, high throughput, and safe operations. The facility supports efficient processing from raw material handling to finished biomass products.

STORAGE & LOGISTICS

Biomass pellet storage at Ayo Biomass M’Drắk plant in Dak Lak Province
Biomass pellet storage at Ayo Biomass M’Drắk plant in Dak Lak Province

Large-capacity covered storage enables secure biomass handling and stable supply throughout the year. The plant’s layout supports efficient logistics and product readiness for export markets.

To support efficient export operations, Ayo Biomass is developing a dedicated pellet storage facility with a capacity of 50,000 metric tons, strategically located near South Van Phong Port.

Pellet storage facility under construction near Nam Vân Phong Port, scheduled for completion in Q2 2026
Pellet storage facility under construction near Nam Vân Phong Port, scheduled for completion in Q2 2026

This storage hub is designed to ensure rapid vessel loading, reduced port waiting time, and reliable shipment schedules, strengthening Ayo Biomass’s ability to serve international customers with consistent supply and high operational efficiency.